Application of non-welded joint in duplex construction Leave a comment

Due to the need for a storage space due to an increase in the amount of goods in a short period of time, it is a duplex to be demolished after temporary use.
Short-term construction of a duplex of more than 90 pyeong
Currently unable to move goods
Square pipe joint is applied to prevent fire hazard
Apply a joint that can be disassembled when dismantling after use

The product was loaded, so it was difficult to assemble, but the assembly was completed in 4 days

Pipe cutting and subassembly

Fixing plate construction for fixing pillars

Construction while the product is loaded
It is possible because it is a non-welded joint

At the same time, the stairs are assembled
It is finished by stewing without welding.
This applied staircase is 1.5m wide and wider than the general staircase, and the center has been reinforced.