In order to use the lower part of the factory-type apartment as an assembly and processing plant, and to use the duplex for multiple purposes.
A square pipe joint that can be disassembled and moved and reassembled later is applied
Many people can work at the same time, so the process can be shortened.
This was done over the course of one day
The stairs are also prefabricated
When the drawing is complete, the pipe is cut and shipped.
Prefabricated stairs are also in progress.
When the drawing is complete, the pipe is cut and shipped.
Based on the drawings, the sub-assembly team and
The work is carried out at the same time by dividing the basic anchor work team into the stair work team and the assembly team.
Since the floor finish is planned with plywood, the spacing of the base frame must be precise.
Base plate work in progress
When the partial reforestation team completes the joint for the column, the assembly team distributes and builds it.
Once the structure is formed, the stair assembly team begins assembly in earnest.
Ready for plywood laying work
It’s a one day job